GAO decisions/Denied/Decided 29 Jul 2026
DCS Corporation
Reasonableness and scope of corrective action
The procurement
The Army competed a task order for systems engineering and technical assistance (SETA) support services under its Responsive Strategic Sourcing for Services (RS3) multiple-award IDIQ contract. It awarded to Amentum Services, Inc. at a total evaluated price of $251,658,252, took corrective action after protests, and selected Amentum again in January 2026. Four offerors, including DCS and Amentum, reached the final phase of the competition.
The protest
In its second protest, DCS showed that a firm Amentum had named as a small business subcontractor was actually a large business. The other two finalists had already been found unacceptable on small business participation, so a correct evaluation would have left DCS the only eligible offeror. Instead, the Army amended the RFP's small business participation terms and let all four offerors revise their small business participation, cost/price, key personnel and OCI volumes. DCS argued the corrective action was tailored to let Amentum, and only Amentum, repair its proposal, and pointed to an evaluator's email describing a position as transitioning to the SETA contract with Amentum.
The agency’s answer
The Army said it concluded the RFP's small business participation terms were potentially ambiguous and its evaluation under them unreasonable, and that three of the four offerors had been excluded because of that same provision. Fixing it opened the door for three offerors, not just Amentum, and every offeror could revise its cost/price volume. The evaluator who wrote the email was not involved in approving the corrective action.
What decided it
Agencies have broad discretion over corrective action, and this one was reasonably tailored to the flaw the Army found.
GAO denied DCS's challenge to the scope of the corrective action and dismissed other parts of the protest. The details of corrective action are within the agency's sound discretion, and GAO will not object as long as the action is appropriate to remedy the concern that prompted it. The Army reasonably concluded that ambiguous small business participation terms had excluded three of four offerors, and letting all offerors revise the affected volumes did not appear tailored to benefit any particular firm. The evaluator's email was not the convincing proof needed to show bad faith.
“The details of a corrective action are within the sound discretion and judgment of the contracting agency, and we will not object to any particular corrective action, so long as it is appropriate to remedy the concern that caused the agency to take corrective action.”
GAO, B-423820.6
For the file: When a protest exposes a solicitation flaw that knocked out most of the field, the agency may fix the flaw and let everyone revise rather than award to the last firm standing, as long as the file ties the scope of the revisions to the problem found.
Read the decision at GAO →
Facts are condensed from the published decision and the quote is verbatim; the takeaway is ours. Where GAO decided several grounds, only this one is described.