GAO decisions/Sustained/Decided 16 Apr 2024
Criterion Corporation
Price realism analysis ignored the offeror's technical approach
The procurement
Base operations support services at Homestead Air Reserve Base, Florida, under an IDIQ contract with fixed-price, time-and-material, and cost-reimbursable orders. Step one screened prices for completeness, fairness, reasonableness, balance and, if necessary, realism. Step two looked at technical acceptability starting with the lowest price, then selected the best combination of price and past performance.
The protest
Criterion argued that the Air Force unreasonably excluded its proposal as unrealistically low. The agency compared Criterion's staffing count and price to the second-low offeror's, but never examined Criterion's own labor mix or how it planned to use its workforce to do the work.
The agency’s answer
The Air Force said it did examine Criterion's technical approach. Criterion proposed more full-time equivalents than the next-lowest offeror at a much lower price, with labor rates only marginally lower on average. The price analyst concluded it was unrealistic to think Criterion could propose more FTEs for much less and still accomplish the scope of work.
What decided it
The realism analysis had to account for the offeror's own labor mix and staffing approach, not just its FTE count and price.
GAO found that the record did not show the Air Force considered Criterion's labor mix, labor utilization strategy, or whether its FTEs and labor categories could realistically support each performance work area at its unit prices. Without that, the comparison to the second-low offeror was not apples-to-apples. GAO recommended a new price realism evaluation that considers whether Criterion's price shows a misunderstanding of the requirements or inordinate performance risk, plus reimbursement of Criterion's protest costs.
“Although the Air Force argues that it examined the respective numbers of proposed FTEs, the record does not show that the agency considered Criterion's technical solution to include its proposed labor mix (i.e. the types and experience levels of the proposed workers) or labor utilization strategy when concluding that the firm's proposed price was unrealistic.”
GAO, B-422309
For the file: Before you exclude a low price as unrealistic, the price analysis has to open that offeror's technical volume and test its labor mix and staffing plan. A comparison of head count and price against the next offeror is not a realism analysis.
Authorities: FAR 15.404-1(d)(3). Read the decision at GAO →
Facts are condensed from the published decision and the quote is verbatim; the takeaway is ours. Where GAO decided several grounds, only this one is described.
Could you have called it?
Protest! is the daily game: three real GAO decisions, both sides laid out. Rule sustain, deny or dismiss, then pick what decided it.