GAO decisions/Dismissed/Decided 14 Nov 2023
Lunar Resources, Inc.
Award of an other transaction agreement (Funded Space Act Agreement)
The procurement
NASA's Tipping Point announcement for partnership proposals (AFPP) No. 80HQTR22SOA02 sought proposals to advance commercial space technologies in two areas: cislunar/lunar surface infrastructure and in-space infrastructure. It anticipated Funded Space Act Agreements of one to four years, with approximately $150-200 million in total funding for all selections, and said the evaluation would not follow the FAR or the NASA FAR Supplement because the announcement would not result in a contract. NASA selected 11 firms, including Blue Origin, LLC.
The protest
Lunar Resources (LRI), which was not selected, argued that Blue Origin was not entitled to award because its proposal contained fraudulent representations. It first raised the allegation with NASA, asking the agency to rescind Blue Origin's award or withhold its funding until NASA investigated. When the agreements officer found no basis for further action, LRI filed an identical protest at GAO.
The agency’s answer
NASA asked GAO to dismiss. It argued that it awarded the Funded Space Act Agreement to Blue Origin under its other transaction authority in the Space Act, not through a competition under the FAR, so GAO lacked jurisdiction to consider the protest.
What decided it
An OT agreement isn't a procurement contract, and LRI didn't claim NASA misused its OTA to avoid using one.
GAO dismissed for lack of jurisdiction. Its bid protest authority under CICA covers the award of contracts for the procurement of goods and services, and agreements an agency issues under its other transaction authority are not procurement contracts. The exception is a timely, pre-award protest alleging the agency is improperly using its OTA to avoid a procurement contract. LRI's challenge was confined to the evaluation of Blue Origin's proposal and the award, so it fell outside the exception.
“The exception to this general rule is a timely, pre-award protest alleging that the agency is improperly exercising its OTA to avoid using a procurement contract.”
GAO, B-421936
For the file: GAO won't referee who wins an OT or Space Act agreement. A firm that believes an agency is using OT authority to avoid the FAR has to bring that objection to GAO before award; complaints about the evaluation afterward will be dismissed.
Authorities: 51 U.S.C. § 20113(e); 31 U.S.C. § 3551(1); 4 C.F.R. § 21.1(a). Read the decision at GAO →
Facts are condensed from the published decision and the quote is verbatim; the takeaway is ours. Where GAO decided several grounds, only this one is described.