First-tier subcontract reporting
$40,000was $30,000 until 1 Oct 2025
- Citation
- FAR 52.204-10(d)(2); FAR 4.1403(a)
- Last moved
- 1 October 2025, from $30,000
- Checked
- 2 November 2026, against the codified FAR and, where it leads the FAR, the statute
- Note
- Quiet change, real compliance consequence. The clause points to the 4.1403(a) figure in effect on the date of the subcontract award, so primes still using $30,000 are reporting subawards they no longer have to.
A prime contractor awards a first-tier subcontract under a contract that carries the subaward reporting clause. At or above what subcontract value must the prime report it by the end of the following month?
$40,000 (FAR 52.204-10(d)(2); FAR 4.1403(a)), as of 2 November 2026. It was $30,000 until it moved on 1 October 2025.
Get told when this figure moves
Leave an address and we will email you when this figure changes, with the new amount and the citation.
One email each time it changes, and nothing else: this is not the weekly list. We send a link first to confirm the address is yours, and every alert carries a link that stops it. What we keep.
Before you rely on it: this is the codified amount in effect on 2 November 2026. Agencies on a Revolutionary FAR Overhaul class deviation use the same value under a different paragraph number, and your agency supplement can set a lower one. Check it against the current text before it goes in the file.
Two ways to use it
Have a number? Dollar check takes the value of your buy and tells you which thresholds apply, with the approvals it needs.
Open Dollar checkWant them cold? Threshold is the daily game: five figures, three guesses each.
Play today’s ThresholdBonds, reporting, responsibility, CAS and other transactions
6 more- Prototype OT — head of contracting activity approval$100,000,000
- Prototype OT — senior procurement executive and congressional notice$500,000,000
- Miller Act performance and payment bonds$150,000
- CAS full coverage threshold$100,000,000
- CAS applicability — negotiated contract exemption$35,000,000
- Subcontracts with excluded parties — compelling reason threshold$45,000