FAR 52.242-14
Suspension of Work

Clause date
APR 1984
Prescribed at
FAR 42.1305(a). Insert in solicitations and contracts when a fixed-price construction or architect-engineer contract is contemplated.
Applies to
Fixed-price construction and architect-engineer contracts.
Flowdown
No flowdown required
52.242-14 contains no paragraph requiring its insertion in subcontracts. It is not listed in 52.244-6(c)(1) or 52.212-5(e)(1).
Full text
FAR 52.242-14 on Acquisition.gov

… (a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government. …

From the clause · Codified FAR · FAC 2026-01

Why it matters: The adjustment for an unreasonable suspension excludes profit, and costs incurred more than 20 days before the contractor's written notice are not recoverable unless the delay came from a suspension order.

This is the codified text, not any agency's Revolutionary FAR Overhaul deviation. An agency running a class deviation may have this clause renumbered, rewritten or prescribed differently — check the deviation before you put a clause in a solicitation.

Know your clauses?

Clause & Effect is the daily game: five passages of real clause text with the giveaway words blacked out. Name the clause, then the section that prescribes it.

Play today’s Clause & Effect

More Part 42 clauses

2

This Week, in your inbox every Monday.

One email a week: what changed, what got decided, and what it means for the file on your desk. Written by practitioners, for the people who run the competitions.

Mondays · no vendor pitches · one-press unsubscribe

We email you a link to confirm the address is yours. It is used for the weekly issue and nothing else.